Free template · no email required
Free construction schedule template for Excel and Google Sheets
Two ready-to-edit construction project schedule templates, a new single-family home and a kitchen remodel, with every task, its trade, its duration and what it waits for. Download the CSV, open it in Excel or Google Sheets, and adapt it to your job. Below: a worked construction schedule example as a Gantt chart, and the steps to build your own.
Updated October 4, 2026 · for remodelers, small builders and specialty trades
Download the construction schedule template
New home construction schedule (26 tasks)
From plans and permit to certificate of occupancy: site work, foundation, framing, rough-ins, inspections, finishes and closeout. 134 working days with the example durations.
Download the new home template (CSV)Kitchen remodel schedule (22 tasks)
Design, permit, demolition, rough-ins, inspection, cabinets, countertops and trim-out. 48 working days with the example durations. It is the example charted below.
Download the remodel template (CSV)Free, no email, no sign-up. CSV opens directly in Excel (File > Open), Google Sheets (File > Import), Numbers or LibreOffice. Save it as .xlsx or keep it in Sheets once it is open.
What is in each row
- ID and predecessors: each task has a number, and the Predecessors column lists the tasks that must finish before it can start (finish-to-start). This is what turns a task list into a schedule.
- Phase, task and trade: phases group the work (site work, foundation, framing, rough-in, finishes, closeout), and the trade column tells you which crew or subcontractor you need to book.
- Duration in working days: example values to replace with your own. Count working days, not calendar days, so weekends and holidays stay out of the math.
- Start and finish day: already calculated from the durations and predecessors (day 1 is the first working day of the job). Fill the planned dates once you know your start date.
- Assigned to, status and notes: the crew lead or sub you booked, where the task stands, and what to watch (weather-sensitive tasks are flagged).
The durations are realistic starting points for a small job, not a standard. Permit review, inspection lead times and supplier lead times vary by city and by supplier: replace them with the numbers your building department and suppliers give you.
Construction schedule example: a kitchen remodel on a Gantt chart
Here is the kitchen remodel template drawn as a Gantt chart. Each bar is a task, its length is its duration in working days, and it starts when its last predecessor finishes. With the example durations, the job runs 48 working days, about 10 weeks.
- Design, selections and contractGeneral contractor
- Permit application and approvalGeneral contractor
- Order cabinets and long-lead itemsGeneral contractor
- Cabinet lead time (build and delivery)Supplier
- Protect floors, set up dust barriersGC crew
- Remove cabinets, counters and flooringDemolition
- Framing changes and blockingCarpenter
- Plumbing rough-inPlumber
- Electrical rough-inElectrician
- Vent hood ductHVAC
- Rough-in inspectionInspector
- Insulation, drywall hang and finishDrywall
- Prime and first coat of paintPainter
- FlooringFlooring
- Cabinet installationCabinet installer
- Countertop templateCountertop fabricator
- Countertop fabrication and installCountertop fabricator
- Tile backsplashTile setter
- Plumbing and electrical trim-out, appliancesPlumber, electrician
- Final paint and touch-upsPainter
- Final inspectionInspector
- Punch list, clean and walkthroughGC crew
Notice what drives the finish date: not demolition or drywall, but the cabinet lead time. The cabinets are ordered in the first week and take five weeks to arrive, so the flooring crew could be done days before there is anything to install. On a real job, that is the line to confirm with the supplier first, and the reason to order long-lead items as soon as the design is signed.
The second lesson is the chain after the cabinets: template, fabrication and install of the countertops take more than a week on their own, and the backsplash and plumbing trim-out cannot start before. Clients often expect the kitchen to be usable the day the cabinets go in. Showing them this chart early avoids that conversation at the worst moment.
How to build a construction project schedule in 7 steps
List the phases, then the tasks
Start from the estimate: every line of work becomes one or more tasks. Group them by phase (site work, structure, rough-in, finishes, closeout). Keep tasks at the level a crew can own: "electrical rough-in", not "run wire to bedroom 2".
Assign a trade to each task
Write who does it: your own crew or a named subcontractor. Tasks without an owner are the ones that slip.
Estimate durations in working days
Use your past jobs first, then your subs' input. Ask each sub how many days they need on site and what they need finished before they come.
Link each task to what it waits for
For every task, write the tasks that must be complete first: drywall waits for the rough-in inspection, cabinets wait for flooring and for delivery. Most links on a small job are finish-to-start.
Add lead times and inspections as tasks
Permits, material lead times and inspections take calendar time even if nobody from your company works on them. Put them in the schedule as tasks with their own durations, or they will surprise you.
Find the critical path and set the dates
The longest chain of linked tasks sets the finish date. Pick the start date, turn working days into calendar dates, and check the critical tasks twice: those are the ones to protect.
Share it and update it every week
Send each crew and sub their dates, confirm the next two weeks every Friday, and update the schedule when something moves. A schedule nobody updates becomes wrong within a week.
Construction timeline template: the phases of a new home
The new home template follows the usual order of a wood-frame single-family house. With its example durations it runs 134 working days from the start of design. Your timeline will differ, but the sequence rarely does:
| Phase | What happens | What usually drives it |
|---|---|---|
| Pre-construction | Plans, engineering, selections, permit | Permit review time and client decisions |
| Site work and foundation | Stake-out, excavation, footings, walls or slab, backfill | Weather, footing inspection, concrete availability |
| Framing and dry-in | Framing, roof, windows and doors | Framing crew size and weather; the house must be dried in before interior work |
| Rough-ins and inspections | Plumbing, electrical and HVAC rough-in, then inspections | Getting three trades in the right order, inspection lead time |
| Interior | Insulation, drywall, paint, trim, cabinets, flooring | Drywall drying time, cabinet and countertop lead times |
| Finishes and closeout | Trim-out, fixtures, final inspections, punch list | Final inspection availability and punch list discipline |
Exterior work such as siding, driveway and grading runs in parallel with the interior once the house is dried in. That is where a construction timeline template saves the most time: you see which crews can work at the same time without being in each other's way.
Making the template work in Excel or Google Sheets
Put your start date in a spare cell (say N1), then fill the planned dates with the working-day function, which skips weekends and an optional list of holidays:
Planned start date: =WORKDAY($N$1, G2-1)
Planned finish date: =WORKDAY($N$1, H2-1)
- Both Excel and Google Sheets have WORKDAY. Add a holidays range as the third argument if your crews do not work on public holidays.
- To draw bars in the sheet, add one column per week and use conditional formatting to color a cell when the week falls between the start and finish dates.
- Freeze the first three columns so the task names stay visible when you scroll across the weeks.
- Share a view-only link with subs, and keep editing rights to one person: two people editing the same schedule is how versions drift.
One limit to keep in mind: the start and finish days in the CSV are values, not formulas. If you change a duration, recalculate the start days of the tasks that follow, or rebuild them with a MAX formula over the predecessors' finish days.
When a spreadsheet schedule stops working
A spreadsheet is the right tool for one job at a time and a schedule that rarely changes. It starts to hurt when a rain day pushes the footings and you have to move fifteen rows by hand, when two jobs share the same framing crew, or when a sub shows up on the date from last week's version.
That is what we are building Jobsite Scheduler for: it drafts this kind of schedule from your estimate, moves every dependent task when you flag a delay, and texts each crew and sub their new dates, with no account for them. It is in development; join the early access list to try it first, and founding members keep 50 % off for life.
Questions, answered
Is the construction schedule template really free?
Yes. The CSV files download directly, with no email, no sign-up and no watermark. You can use and modify them for your own jobs and your clients.
Does the template work in Google Sheets?
Yes. In Google Sheets, use File > Import > Upload and pick the CSV. Accents and dashes display correctly. The WORKDAY function works the same as in Excel.
Are the durations in the template accurate for my job?
They are examples for a small job, meant to be replaced. Permit review, inspections and supplier lead times vary a lot between cities and suppliers, and crew size changes every duration. Use your past jobs and your subs' estimates.
What is the difference between a construction schedule and a construction timeline?
A timeline shows the phases and key dates, usually for the client. A schedule goes down to tasks, durations, dependencies and who does what, for your crews. The template gives you the schedule; collapse it to phases when you need a client timeline.
What is the critical path in a construction schedule?
It is the longest chain of tasks that depend on each other. Any delay on one of those tasks delays the end of the job. In the kitchen example, the cabinet lead time is on the critical path, so it deserves more attention than tasks with slack.
Keep reading
More free resources
Free construction scheduling software
An honest comparison of the free and low-cost options, from spreadsheets and Gantt tools to the free plans of construction apps, with prices checked in October 2026.
See the comparisonConstruction crew scheduling
How to schedule your own crews, employees and subcontractors, and how to tell them when the job moves, with a checklist of good practices.
Read the guideFrom estimate to schedule, without the spreadsheet
Jobsite Scheduler will draft the schedule from your estimate and keep every crew on the right dates. Join the early access list to try it first.